Building With Provident Homes 

 

Phase 1:  Project Development Process

1) Initial Design Meeting

  • Needs Analysis

  • Homeowner’s Wish List

  • Ideal Floor Plan

  • Present Magazine Pictures

  • Rough Cost Data

  • Give scope of project

  • Budget Talks

2) Conceptual Design Development

  • 1/8" Scale

  • Design Sketches & Diagrams

  • Develop Spatial Relationships

  • Develop Conceptual Pricing

3) Preliminary Design Development

  • 1/4" Scale

  • Home Elevations & Floor Plans

  • Develop Preliminary Specifications

  • Prepare Preliminary Cost Estimate

 

4) Preliminary Plan Revision

  • Continued Plan Refinement

  • Budget Related Changes

5) Final Construction Documents

  • Complete & Thorough Set of Documents to Build Structure

  • Completion of Final Plans

  • Completion of Final Specifications

  • Completion of Final Construction Cost Estimate

6) Contract Signing

  • Approval of Final Cost Estimate

  • Approval of Final Plans & Specifications

 

Phase 2:  Construction Process

1) Pre-Construction Meeting

   A) Meet the Team:

  • Construction Manager
    -  Facilitates day to day construction
    -  Interfaces with clients (homeowners)

  • Selection Coordinator
    -  Guides selection process for home design elements
    -  Meets with clients & vendors in selection process
    -  Arranges on-site confirmation of client’s selections

  • VP & Project Coordinator
    -  Oversee management of project
    -  Maintain & Update project documents
    -  Facilitate communication during project

   B) Review Plans & Contracts

   C) Receive Custom Home Selection Manual

  • Includes specifications, allowance & change order summary, home purchase & sale agreement

  • Projected selection schedule & project schedule

  • Finish schedule

  • Vendor list

2) Physical Construction of Home

   A) Project Schedule

  • Footings, Foundations & Framing (2 Months)

  • Plumbing & Mechanical Rough, Roof (2 Weeks)

  • Electrical & Structured Wiring Rough, Brick (1 Month)

  • Insulation, Drywall, Boxing & Siding (1 Month)

  • Wood Flooring, Interior Trim, Cabinets, Tile (1 Month)

  • Interior & Exterior Painting, Gutters (1 Month)

  • Plumbing, Mechanical & Electrical Trim Out (1 Month)

  • Hardwood, Hardware, Carpet, Shelving (3 Weeks)

  • Punch, Rough Clean & Final Clean (2 Weeks)

   B) Selection Schedule

  • Stage 1 – Exterior Finish, Windows, Roof, Front Door & Exterior Paint

  • Stage 2 – Appliances, Plumbing Fixtures, Cabinets, Stairs, Built-Ins, Fireplace Mantels & surrounds

  • Stage 3 – Structured Wiring, Tile, Drywall Options, Interior Doors & Trim, Garage Doors, Interior Paint Colors, Counter tops

  • Stage 4 – Lighting, Hardwood Floors (stain), Carpet, Door & Bath Hardware, Closet Shelving & Mirrors

  • Stage 5 – Driveway Design/Finish, Landscape Plans, Exterior Railings

Phase 3:  Post Construction

1) Closing / Post Construction Meeting

     A) Sign closing documents

     B) Receive 2-10 Warranty Binder

     C) Receive Provident Homes 1 Year Warranty Information

2) Warranty Program

     A) Warranty Service Coordinator

  • Facilitates resolution of closing

  • Receives & formats 60 day & 1 year warranty requests

  • Assists Warranty Manager with scheduling subcontractors & vendors for warranty work

     B) Warranty Manager

  • Assists with punch activities related to closing

  • Schedules subcontractors & vendors for warranty work

  • Facilitates completion of work for 60 day & 1 year warranty requests

 

Back to Distinctions Page